March 11, 2025 Permanent Municipal Building Committee

March 21, 2025
1 min read

City Point Partner’s Project manager Kim Treacy reported that most interior work on the Council on Aging/Community Center, including tiling, flooring, and fixture installation, is nearly complete. However, delays in securing full sized permanent power from Eversource have extended the project timeline. The electrical and mechanical teams are scheduled to initiate testing and commissioning once power is established.

Initially expected to be completed by February 11, the timeline has shifted, with substantial completion now set for April 11 and final completion by May 5. Committee members discussed mitigating further delays by advancing punch list inspections of mechanical, electrical, plumbing, and fire protection systems.

The committee also examined financial impacts, with updated budget sheets reflecting adjustments. A shift from a full kitchen to a serving pantry reduced the kitchen equipment allocation from $90,000 to $10,000. Other revisions include removing commissioning costs due to in-house inspections, updating building envelope fees, and revising moving expense estimates from $10,000 to $5,000 as much of the work will be handled by town staff. 

Additional change order costs include $55,000 for extended general conditions into April. The committee opted to monitor these expenses weekly, with an agreement that unused funds will be credited back. The current budget balance stands at approximately $121,000 after accounting for these adjustments. Pending expenses include $40,000 for site lighting and $20,000 for a MassDOT-mandated emergency access gate on Route 20.

The committee approved multiple change orders but emphasized the importance of detailed and regularly updated schedules to prevent last-minute cost escalations. They noted that delays in power connection and late reconfigurations by the Planning Board to the solar canopy changed the site lighting and impacted the overall timeline and budget.

Progress on the three part library renovation was reported. The elevator contractor has been onboarded, with procurement underway and construction set to begin in June. Interior renovations are almost complete, with remaining finishing touches on light fixtures and final hardware installations. The bathrooms have reopened. The site improvements project, delayed due to winter conditions and design modifications, is addressing issues of unevenly matched pump capacity related to sewer tie-in to the town wastewater system. The proposed solution, modifying existing pump cycles, was approved by town engineers and the Board of Health.

The Loker Recreation Field project is still awaiting the contractor to deliver a full size as-built plan as required by Conservation before an official closeout can take place. Construction work on the field was completed in the fall 2023 and the field played on in 2024 spring and fall season. 

The remaining payment due on the Stone Bridge project stands at $50,271, pending resolution of contractor disputes. The landscape work has been completed.

Latest from Blog

WaylandCAN celebrates a ‘Roaring Night’ 

Wayland residents came together in style Dec. 6, as the Wayland Community Action Network (WaylandCAN) hosted A Roaring Night of Connection at Sandy Burr Country Club, drawing over 100 community members for

Local Artist Brings Wayland Landscapes to Life

While Wayland resident Emily Rubinfeld’s artistic journey has taken her through numerous changes, she now spends most of her time creating acrylic and watercolor renditions of landscapes around Wayland, particularly around Heard

Wayland Police Chief Ed Burman retires

Police Chief Edward Burman, 62, retired from the Wayland Police Department on Dec. 19. Lt. Mark Hebert was sworn in Dec. 22 as acting police chief. He served almost four years of

The Dover Amendment and the Planning Board’s decisions

In 2025, the Planning Board navigated complex and often competing considerations, weighing the concerns of taxpaying residents seeking to preserve the town’s pastoral neighborhoods alongside nonprofit organizations asserting that the Dover Amendment

Viewer’s Top 10 of 2025

By Wayland Post Staff A lot has happened in Wayland in 2025. But what does your local publication think were the biggest and most important? From contentious projects – both of the

Public Safety Log

December 15, 2025 – January 4, 2026 Monday, Dec. 158:13 a.m. — A resident of Old Connecticut Path called to report her mailbox was damaged.2:29 p.m. — Two-car motor vehicle accident at

New Cafe Brewing Up Community and Connection

Kirstyn Lipson long dreamt about creating a business centered around food and community. This summer that dream will materialize in a new restaurant, Town House Cafe & Bistro.Following the Nov. 18 Zoning