As a 12-week rehabilitation project shuts down Sherman’s Bridge, commuters are being forced to find alternative routes.
The bridge, which spans the Sudbury River between Sherman’s Bridge Road in Wayland and Lincoln Road in Sudbury, has been closed to all traffic since Nov. 9. The bridge is expected to reopen by Feb. 1, 2027, weather and other conditions permitting.
While the bridge is closed, drivers have to take detours using Routes 27 and 117 with connections through Concord Road and Route 126. Director of Public Works Tom Holder said additional travel time depends on drivers’ starting point and destination, making it difficult to estimate how much longer a person’s commute will take.
For residents who regularly cross Sherman’s Bridge, the closure has meant adjusting their daily travel routes and navigating through increased traffic along other roads.
Lynn Stotz, a Wayland resident of 35 years, said she previously used the bridge three to five times a week to travel between Wayland and Sudbury. Stotz said she has already noticed heavier traffic along some of the alternative routes, especially during the evening commute. “The other day, I could see that the traffic was incredibly heavy on Glezen Lane and Route 27,” said Stotz. Stotz said she thinks the rehabilitation project is necessary, but she questioned the timing of the construction during the holiday season.
“I would say it’s a little bit of an inconvenience, but I do think it’s worth it given that they’re going to upgrade the bridge,” Stotz said.
Emergency response
Wayland Fire Chief Neil McPherson said the closure is unlikely to significantly affect emergency response times because the bridge marks the town boundary, leaving firefighters plenty of alternatives. “We have access to all of the properties in Wayland, so it really doesn’t obstruct our ability to get to addresses in Wayland, and Sudbury can still get to all of the addresses in Sudbury,” he said.
McPherson said Wayland maintains a mutual aid relationship with neighboring communities, including Sudbury, Lincoln, and Weston, allowing additional firefighters and emergency vehicles to respond when needed.
He said he has coordinated with Sudbury’s fire chief to make sure firefighters are aware of the closure and prepared to use alternative routes when responding to emergencies across town lines.
McPherson said the closure for repairs was much better than an unexpected bridge failure. “I would much rather have a planned update of a bridge, which is going to take three months, than an emergency closure which can take much longer,” he said.
Weather could be a factor
Holder said winter weather remains the greatest uncertainty around the construction schedule. Significant snowstorms could delay completion of the project and potentially extend the closure beyond 12 weeks, he said.
Holder urged residents to be patient as construction moves forward. “This type of work requires these inconveniences, but at the end of the project, the resulting bridge will be well worth it,” he said.
The project includes replacing the bridge’s wooden deck, installing new railings and guardrails, and making structural repairs to improve safety for drivers, cyclists, and pedestrians.
Holder noted that the bridge has deteriorated over the past few years despite annual repair efforts from both Wayland and Sudbury and is in “dire need of rehabilitation.” He said officials recognize the inconvenience the closure would cause residents but considered the repairs important.
“They need to completely dismantle the deck and rail system,” he said. “We know from the designers and the contractors that this rehabilitation work was not possible with a partial closure of the bridge.”
This story is part of a partnership between the Wayland Post and the Boston University Department of Journalism’s Newsroom program.